For an explanation of this tool click here.
European PBN Implementation Handbook for Airspace Planners Activities 1 to 17 with critical milestones |
||||
---|---|---|---|---|
ACT | (to be read from bottom-up) | No of Days (Reset Values) |
Key dates (latest)
5 day week |
Notes |
17 | Post Implementation Review (e.g. 6 months after project implementation) | |||
16 | Implementation of Airspace Change (Match AIRAC Cycle date) | << Enter INTENDED Implementation Date here (Must match AIRAC Cycle Date) | ||
Additional working day buffer to allow for unfore-seen delays (aprox. 10% of total) | ||||
14-15 | ATC System Integration
|
|||
GO / No-Go Decision | ||||
12+13a +13b |
Procedure Design, Ground & Flight and Validation & Flight Inspection + 56 day (1) AIRAC cycles
|
* Separate no. of days not calculated for ATC Training; Above shows that this would occur at the same time as PANS-OPS procedure design or during 56 day final AIRAC cycle | ||
11 | Airspace Concept Validation by Real-Time Simulation (Preparation an Runs) ** | ** Assumes availability of FTS and/or RTS simulator slots, and required specialists & ATCos/pseudo pilots available | ||
11 | Airspace Concept Validation by Fast-Time Simulation (Preparation and runs) ** | |||
10 | Confirmation of ICAO Navigation Specification | |||
6-9 | Finalise Airspace Design & CBA - iteration | |||
9 | Airspace Design: Volumes and Sectors | |||
7 | 2nd Iteration: Airspace Design - Routes and Holds | |||
Public Consultation with Airspace Users and other stakeholders & Comment Review | ||||
Environmental Impact Assessment | ||||
8 | Initial Procedure Design | |||
7 | 1st Iteration: Airspace Design - Routes and Holds | |||
6 | Cost Benefit Analysis - fleet, infrastructure etc | |||
6 | Data collection and agreement on CNS/ATM assumptions incl. Fleet capability; traffic sample etc. | |||
5 | Select Safety Criteria; Determine Performance Criteria and understand Safety Policy Considerations | |||
4 | Analyse Reference Scenario (incl. Data collection of full ATM operations and critical review of current operations) | |||
1-3 | Agree Operational Requirement; Project Planning; Create Airspace Design Team; Agree Project Objectives and Scope | << This is the latest project start date based on a 5 day working week | ||
Total number of working days required for the PBN Implementation Project | TOTAL DAYS | |||
Pre- Start |
Public Awareness and Concept Consultation with preliminary Environmental Impact Assessment and Benefits Case |
This start date for formal consultation would be decided outside the project, but would influence the project start date in green, above.
Note: This date is calculated on calendar days, not working days as previously set.
|
||
Total number of working days needed including public consultation | TOTAL DAYS | Includes the number of days needed for public consultation, if appropriate |
Do you want to leave?
New page: