Implementation Work-cycle & Methodology

An organised workflow and sound project management are key to PBN implementation.

  • Implementation Work-Cycle
  • Implementation Methodology Considerations
  • PLANNING
    • Activity 1 - Agree Operational Requirements
    • Activity 2 - Create the Airspace Design Team
    • Activity 3 - Decide Project Objectives, Scope, Resources and Timescales
    • Activity 4 - Analyse the Reference Scenario
    • Activity 5 - Safety Policy, Safety Plan and Safety & Performance Criteria
    • Activity 6 - Agree Assumptions, Enablers and Constraints including Fleet Profile
    • Consultation within the Planning Phase
    • Making Trade-Offs
    • Regulatory Considerations
  • DESIGN
    • Activity 7 - Airspace Design - Routes & Holds
    • Activity 8 - Initial Procedure Design
    • Activity 9 - Design Volumes & Sectors
    • Activity 10 - Coherency Check: Design versus Requirements
    • Stakeholder Consultation in the Design Phase
    • Design Trade Offs
    • The Need for Iterations
    • Regulatory Considerations
  • VALIDATION
    • Activity 11 - Airspace Concept Validation
    • Project Checkpoint
    • Activity 12 - Finalise Procedure Design
    • Activity 13a - Instrument Flight Procedure Validation
    • Activity 13b - Flight Inspection
  • IMPLEMENTATION
    • Go No - Go Decision Point
    • Activity 14 - ATC System and Integration Considerations
    • Activity 15 - Awareness & Training
    • Activity 16 - Implementation
    • Activity 17 - Post-Implementation Review
  • Safety case development
x
This website or its third party tools make use of cookies to enhance browsing experience and provide additional functionality. If you want to know more or withdraw your consent to all or some of the cookies, please refer to the cookies policy. Accept